AC Permits and Inspections in Sanford, Florida: What HB 803 Actually Changed

A residential air conditioning changeout always requires a building permit in Florida — there is no dollar-amount exemption. HB 803 (2026)'s new sub-$7,500 exemption expressly excludes mechanical and electrical work, so it never applies to an AC changeout, at any price.

01

Read the exemption as a negative

HB 803

HB 803 (2026), ch. 2026-63, effective 1 July 2026, requires local governments to exempt a single-family homeowner or contractor from a building permit for work valued under $7,500. It then excludes, verbatim: “Any electrical, plumbing, structural, mechanical, or gas work performed on property containing a single-family dwelling” — s. 553.79(1)(g)2.b., F.S.. An AC changeout is mechanical work and, at the disconnect, almost always electrical work too — excluded by two of the five named trades, at any price. A project also may not be split into pieces to evade this. The baseline requirement, s. 553.79(1)(a), F.S., continues to control every residential changeout in Sanford.

02

The single-trade inspection — real, but not from this bill

PRIVATE PROVIDER

HVAC replacement is defined as a single-trade inspection at s. 553.791(1)(r), F.S., a category an owner (or their contractor, with written authorization) may elect to have reviewed by a licensed private provider instead of the local building department. This definition already existed in the 2025 statutes, tracing to 2024 legislation — HB 803 amended the surrounding section but did not create this category, and it is not a lighter class of permit. The permit is still required either way.

03

The five-business-day clock, correctly conditioned

TIMELINE

Since 1 July 2026, a local government must approve, approve with conditions, or deny a mechanical permit application for an existing single-family home within five business days of a complete application — s. 553.792(1)(a)1., F.S. — but only when the work is valued under $15,000 and the applicant uses the local government’s own plans reviewer. Many full system changeouts in 2026 price above $15,000, in which case a longer tier of the same statute applies instead. This is not an unconditional five-day guarantee.

04

Notice of Commencement

RECORDING

A Notice of Commencement must be recorded before work begins on a direct contract above the statutory threshold under s. 713.13, Fla. Stat. — currently $15,000 for a one- or two-family residence. Below that figure, no NOC is required before the mechanical permit is pulled.

05

The fee comparison across Seminole County

FEES
Residential mechanical permit fee for an AC changeout, Seminole County
JurisdictionFee as publishedOn an ordinary changeout
Casselberry$200 flat$200, whatever the job costs
Longwood$246.61 flat$246.61, whatever the job costs
Oviedo$50 + $6 per $1,000 of valueabout $104 on a $9,000 contract
Lake Mary0.75% of value, $35 minimumabout $68 on a $9,000 contract
Winter Springs$40 up to $1,000, then $60 + $15 per $1,000about $180 on a $9,000 contract
Altamonte Springsabout 2% of contract priceabout $180 on a $9,000 contract
Seminole County (unincorporated)county mechanical fee schedulethe desk for Midway, Lake Monroe and other unincorporated 32771/32773 addresses

Each row is that city's own published fee schedule, checked against the source linked in its name.